Abstract:In view of the fact that the water stop curtain of super large foundation pit in Shanghai cannot be closed in time, and the difference of construction schemes of adjacent bidding sections, the dewatering measures cannot meet the engineering schedule. The control measures of the water stop curtain of three-axis mixing pile to wind the un-removed workshops, buildings and structures, tubular well instead of light well point in the pit, and layered and zoned earth excavation are taken in the project, which meet the construction schedule of the whole project in order to provide reference for the excavation of the similar super large deep foundation pits in soft soil under complex conditions.