Abstract:Combined with the practices, the design and application of the pile-anchor bracing in a deep foundation pit project nearby water are introduced. Through the field measured data, three-dimensional finite element calculation and m-value method in the current specification, the variations of anchor cable axial force, ground surface settlement and pile body displacement are analyzed. The result shows that the m-value method is hard to really reflect the process of redistribution of internal force in the anchor system caused by anchor cable tension. The maximum displacement value of pile body calculated by m-value method is closer to the measured data, and the ground surface settlement development law and the pile body deformation curve shape calculated by the finite element method are more identical with the measured data. Therefore, in the actual design of foundation pit engineering, at the same time to use the m-value method in the current specification for design, it should be supplemented by the finite element calculation and analysis in order to judge the deformation of foundation pit bracing relatively accurately.