Abstract:It is required to dredge the riverbed foundation trough for the construction of immersed tube of river-crossing tunnel structure. The widening and deep dredging of the foundation trough lead to the insufficient safety of the existing bank protection structure. It is necessary to reinforce again and reconstruct the bank protection structure. Due to good stability, the lattice diaphragm wall does not require an inner support system, and the deformation can be controlled. The lattice diaphragm wall is suitable for the immersed tune tunnel bank protection projects, and can be used as the permanent bank protection structure. Taking Guangzhou Nansha Mingzhu Bay Area River-crossing Channel Bank Protection Project as an example, the application of lattice diaphragm wall in this project is introduced. Its deformation is calculated by the numerical simulation. Its applicability and safety are discussed.