Abstract:In recent years, the TRD thickness soil cement mixing wall construction technology as a new technology of foundation pit enclosure is more and more widely applied. But the challenges at the same time are also more and more big, especially in the complex geological and ultra-deep situations. The technology will be much more difficult to construct. Taking a construction site in Nanjing as an example, the 62-m ultra-deep TRD construction technology and key construction technology crossing gravel layer are specially introduced. It can provide the reference for the construction of similar projects in the future.