Abstract:After metro operation, the filling of overpass abutment roadbed and the construction of pile foundation will cause the adverse impact on the built metro tunnels. In order to ensure the metro safety, the analysis should be carried out before construction. Relying on the influence analysis of the abutment filling and pile foundation construction in K1+105 Meilin Guan Direction of of Caimei Interchange on Shenzhen Metro Line 9, the abutment filling, pile foundation holing pouring and other processes are simulated by the finite element analysis software of PLAXIS 3D. The safety assessment of the existing metro line is carried out, and the corresponding requirements for construction monitoring are put forward. The results show that the metro tunnel is safe and reliable during the abutment filling and pile foundation construction of, and this can be constructed. At the same time, the simulation can provide the guidance for the similar projects.