Abstract:Since 2012, the construction of integrated pipe gallery has been greatly developed in Urumqi, with nearly 550 km of integrated pipe gallery planned. At present, the completed pipe gallery is tens of kilometers long. Due to different engineering characteristics, geological and boundary conditions, new problems will be encountered in the building process of a now project. Based on an engineering example of an integrated pipe gallery in Urumqi, this paper discusses the related problems in the design process. Some problems are put forwarded mainly in this paper, including the new method for the feeding port of two compartment pipe gallery, the anchoring problem of longitudinal reinforcement at the support of standard section, the stress problem of pipe gallery when passing through the new vehicle underpass and the additional load of pipe gallery caused by the retaining wall near the viaduct approach. Through analysis, the corresponding solutions are obtained for reference in similar engineering design.