Abstract:Aiming at the disease problems of "bridgehead bump", the causes are analyzed. The technical characteristics of geopolymer grouting reinforcement technology are briefly introduced. Through the introduction of the practical engineering cases, the effect of geopolymer grouting reinforcement technology in the treatment of "bridgehead bump" disease is analyzed in detail. In order to increase the strength and bearing capacity of the subgrade behind the abutment, the geopolymer grouting reinforcement technology is used to reinforce the filling behind the abutment of a bridge in an area of Zhejiang. The effect of grouting reinforcement is evaluated and analyzed through the settlement monitoring of each position of the road and bridge connecting section. By using the geopolymer grouting reinforcement technology, the "bridgehead bump" disease caused by backfill earthwork subsidence and soft soil subgrade settlement is improved and delayed.