Abstract:In order to increase the traffic capacity of the interchange node of Taihedong Bridge, a scheme analysis and study was carried out on the project of widening and reconstructing the main line of Taihedong Bridge. After combing the current conditions, interpreting the planned scheme and analysing the project function, the design principles for the widening and reconstruction of project are determined. In this paper, the three reconstruction schemes of widening on both sides, building on both sides and building on the east side are compared and contrasted. The recommended scheme of building on the east side is reviewed from the three aspects of flat line position, vertical section, cross-section and pavement structure. It is summarized in this paper how to transform the interchange node to meet the traffic demand on the basis of using existing resources and avoiding large scale demolition and construction.