某地铁施工穿越既有电力隧道节点处理方案研究
作者:
  • 摘要
  • | |
  • 访问统计
  • | |
  • 相似文献
  • | | |
  • 文章评论
    摘要:

    城市地铁施工过程中,经常会遇到各种各样的地下障碍物,这是需要建设者需要解决的施工难点之一。本文依托郑州地铁1号线一期紫荆山站工程,介绍其在施工过程如何处理一超高压电力隧道的处理方案。实践表明,推荐方案既可确保地下连续墙、支护结构和土方开挖的顺利进行,又可确保周边环境安全,为后续类似工程施工提供了参考。

    Abstract:

    In the process of urban subway construction, various underground obstacles are often encountered, which is one of the construction difficulties that need to be solved by builders. Based on the Zijingshan station project of phase I of Zhengzhou Metro Line 1, this paper introduces how to deal with an ultra-high voltage power tunnel in the construction process. The practice shows that the recommended scheme can not only ensure the smooth progress of diaphragm wall, support structure and earth excavation, but also ensure the safety of the surrounding environment, which provides a reference for the construction of similar projects in the future.

    参考文献
    引证文献
    网友评论
    网友评论
    分享到微博
    发 布
引用本文

林林.某地铁施工穿越既有电力隧道节点处理方案研究[J].城市道桥与防洪,2022,(6):179-181.

复制
分享
文章指标
  • 点击次数:44
  • 下载次数: 297
  • HTML阅读次数: 0
  • 引用次数: 0
历史
  • 收稿日期:2022-03-15
  • 最后修改日期:2022-03-23
  • 录用日期:2022-04-03
  • 在线发布日期: 2022-07-17
关闭