Abstract:The Xishan District Sewage Treatment Plant has undergone four-phase renovation, and now the quality of the effluent cannot meet the discharge requirements of the new standard. The current phase of the project is carried out on the basis of the processing capacity of the branch, and only upgrading and renovation will be carried out without capacity expansion. The pretreatment process adopts emergency tank and buffer tank, middle grid and shallow air flotation tank, and the advanced treatment process adopts ozone catalytic oxidation tank, nitrification filter tank, filter cloth filter tank and denitrification filter tank. The process design of each monomer is introduced. . The project was completed in September 2019, and the operation effect always meets the emission requirements.