A bridge is a double-pylon double-span suspension bridge. Its main span is 1688 m long, and its steel box girder of side span is 548 m long. Its west anchorage adopts an underground diaphragm wall with a thickness of 1.5 m as the main enclosure structure for the excavation of the anchorage foundation pit. The underground diaphragm wall is embedded into the medium and slightly weathered mudstones. The excavation depth of the foundation pit reaches 22.2 m, and the soft soil is reinforced by the cement powder sprayed piles. Based on the construction of the anchorage foundation pit enclosure structure for the bridge, the key technologies for the construction of the ultra-deep anchorage foundation pit enclosure structure are discussed, and some construction suggestions are given.