Abstract:The 33# pier of Beijiang Bridge is adopted of bored pile and separated base slab. The base slab is located in the range of weathered mudstone, the water level at the pier is deep and the water velocity is fast. The foundation construction technology is difficult. After research, the construction method of "drilling platform + steel sheet pile cofferdam" is determined. The key technologies of rotary drilling rig pilot hole and underwater high-pressure grouting are adopted for the construction of steel sheet pile cofferdam, and the construction method of pre-excavation and cofferdam dry excavation is adopted for the excavation of bedrock within the range of base slab, which solves the construction problem of low-pile base slab without coating and rock-socketed.