Abstract:The construction of expressway outside the city is growing vigorously, in which the interaction of the important municipal pipelines, such as expressway, extra high voltage line, oil conveying pipe and gas pipe in the urban area is increasing. Taking the Riverside Channel Pudong Section Construction Project as an example and focusing on the node of Zhouhai Substation, the scheme design of expressway under the condition of extra-high voltage lines is studied. Based on the complex construction conditions of extra-high voltage lines, three design schemes of tunnel, ground and "low overhead" are proposed, and are systematically compared and selected. Combined with the pipeline characteristics at the nodes of Zhouhai Substation and the design requirements of the riverside channel project, the ground scheme is comprehensively recommended as the implementation scheme. The research results provide a useful reference for similar projects.