Abstract:In order to solve the engineering problems such as the serious wear of the cutter head, the cutter head jammed, the surface collapse and the muck gushing for the large-diameter earth pressure shield under the conditions of large-particle water-rich pebble-boulder soil stratum, combined with the construction situation of the shield tunneling project between Yongfeng Station and Puyang Station in Dusi Mountain Rail Transit Project DSZQ-1, the research is carried out from the aspects of shield selection and design, advanced geological early warning treatment, tunneling parameter selection, muck improvement and screw anti-surge. The key technology of large-diameter earth pressure shield tunneling in Dujiangyan Area with large-particle water-rich pebbles and boulder soil stratum is summarized, which provides a reference basis for the construction of subsequent construction in such stratum.