钢板梁顶推法施工过程有限元分析
作者:
作者单位:

1.中国轻工业长沙工程有限公司,湖南 长沙 410007
2.中交中南工程局有限公司,湖南 长沙 410002

作者简介:

张娟(1990—), 女, 硕士, 工程师, 从事工程结构设计与技术研究工作。

通讯作者:

中图分类号:

U445

基金项目:


Finite Element Analysis in Construction Process of Steel Plate Girder by Incremental Launching Method
Author:
Affiliation:

1.China Light Industry Changsha Engineering Co., Ltd., Changsha 410007, China
2.CCCC Central-South Engineering Bureau Co., Ltd., Changsha 410002, China

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    为了确保钢板梁顶推法施工过程的安全性,以陕西省平利至镇坪高速白土岭大桥为工程背景,分别对其钢板梁顶推及落梁施工过程进行计算分析,并将计算结果与实际施工过程监测结果进行了对比分析。结果表明:顶推施工过程中主梁结构的刚度、强度及稳定性均满足规范要求,可以安全施工;现场施工过程监测结果与理论计算结果基本吻合,但各项数据的实测值均较理论值偏小,说明理论计算结果相对保守,采用有限元的方法进行计算并指导施工具有较高的可靠性。

    Abstract:

    In order to ensure the safety of the construction process of steel plate girder by incremental launching method, the construction process of steel plate girder pushing and girder falling is calculated and analyzed respectively on the engineering background of Baituling Bridge in Pingli to Zhenping Expressway in Shaanxi Province. And the calculation results are compared with the actual construction process monitoring results. The results show that the stiffness, strength and stability of the girder structure meet the requirements of the code during the incremental launching, which can be safely constructed. The monitoring results of the field construction process are basically consistent with the theoretical calculation results, but the measured values of each data are smaller than the theoretical values, indicating that the theoretical calculation results are relatively conservative. The finite element method is more reliable to calculate and guide the construction.

    参考文献
    相似文献
    引证文献
引用本文

张娟,丁巍.钢板梁顶推法施工过程有限元分析[J].城市道桥与防洪,2025,(2):190-195.

复制
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2023-08-15
  • 最后修改日期:2024-07-10
  • 录用日期:2024-07-25
  • 在线发布日期: 2025-03-01
  • 出版日期:
关闭