Abstract:The construction of underground stations is a key link in the construction and operation of underground rail transit network. How to reasonably organize the construction of underground station according to the practical conditions of the project, it is practically significant to smoothly implement the main construction of underground station under the premise of ensuring the social traffic. Taking the projects of Fenghuangchi Station and Jinniushan Station in Fuzhou Metro Line 4 at the examples, the construction difficulties and technologies of the project are analyzed and compared. Finally, the half-covered excavation sequential method is selected. The main construction technology, the construction site layout and traffic organization of the underground station with the different cover plates are introduced. The main construction of underground station of the project is smoothly implemented under the premise of ensuring the social traffic, which can provide the reference for the similar projects in the future.