受限空间强透水砂层地段涉铁框架护涵施工关键技术
作者:
作者单位:

作者简介:

万伟(1990—), 男, 学士, 工程师, 从事桥梁设计施工工作。

通讯作者:

中图分类号:

TU997;U445.4

基金项目:


Key Technologies for Construction of Railway-related Frame Culverts in Highly Permeable Sand Layer Sections with Limited Space
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    某引水工程下穿京广铁路桥孔,采用明挖基坑现浇框架护涵作为原水管道下穿铁路防护通道。受铁路桥下净空限制,基坑无法采用大型机械设备施工。护涵下穿位置为既有河道河床,受上游水库开闸泄洪影响,河床经常淹没。河床地质主要为粗砂、砂砾等强透水层,地下水与既有河道联通。受铁路桥下空间限制、强透水砂层地质、上游水库开闸泄洪共同影响,基坑止水高压旋喷桩在动水环境下成桩质量差,止水效果不佳,基坑内水位与基坑外地下水联通,由于邻近铁路桥梁作业不得抽取地下水,现浇框架不具备干地作业条件。为减少对既有铁路桥梁的影响,临近铁路在不抽取地下水、不采用大型机械设备的条件下,现浇框架采用部分预制+部分现浇新工艺技术,施工期间对既有铁路桥墩进行位移沉降变形监测,桥墩水平位移影响-1.01~2.30 mm,竖向位移影响-0.12~1.04 mm,实践证明该新工艺临近铁路桥梁施工影响较小。

    Abstract:

    A water diversion project passes through the bridge span of the Beijing-Guangzhou Railway. The excavated foundation pit and the cast-in-situ frame culvert is used as the protection channel of the raw water pipeline to pass through the railway. Due to the limitation of the clearance under the railway bridge, the foundation pit cannot be constructed by the large machinery and equipment. The underpass of the culvert is located on the existing river bed, which is often submerged due to the impact of the opening of the upstream reservoir and the discharge of floodwater. The geology of the riverbed is mainly coarse sand, gravel and other strong permeable layers, and the groundwater is connected with the existing river channel. Affected by the space constraints under the railway bridge, the geology of the strong permeable sand layer and the flood discharge of the upstream reservoir, the foundation pit water-stopping high-pressure jet grouting pile has poor piling quality in the dynamic water environment, and the water-stopping effect is not good. The water level in the foundation pit is connected with the groundwater outside the foundation pit. Due to the fact that groundwater extraction is not allowed for operations near railway bridges, the cast-in-place frame does not meet the conditions for dry ground operations. In order to reduce the impact on the existing railway bridge, near the railway, without extracting groundwater or using large-scale mechanical equipment, a new process technology of partial prefabrication and partial cast-in-place is used for the cast-in-place frame. The displacement and settlement deformation of the existing railway pier are monitored in the construction period. The horizontal displacement of bridge piers is affected by -1.01 to 2.30 mm, and the vertical displacement is affected by -0.12 to 1.04 mm. The practice proves that the new process has little impact on the construction of the adjacent railway bridge.

    参考文献
    相似文献
    引证文献
引用本文

万伟,李乐.受限空间强透水砂层地段涉铁框架护涵施工关键技术[J].城市道桥与防洪,2025,(7):245-247.

复制
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2024-12-30
  • 最后修改日期:2025-07-07
  • 录用日期:2025-03-01
  • 在线发布日期: 2025-07-20
  • 出版日期:
关闭