预留并行盾构穿越条件的深基坑设计与分析
作者:
作者单位:

作者简介:

林楠(1993—), 男, 硕士, 工程师, 从事隧道工程设计工作。

通讯作者:

中图分类号:

U455

基金项目:


Design and Analysis of Deep Foundation Pits with Reserved Conditions for Parallel Shield Tunneling
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    伴随城市地下空间开发进程,新建隧道基坑设计需充分预留下卧远期盾构穿越条件。聚焦上海市外青松公路地道工程,针对新建隧道与远期轨道交通并行的情况,对施工期临时交通受限情况下的基坑设计展开研究。运用有限元软件MIDAS GTS/NX建立计算模型,得到由短地下连续墙与长工法桩组合而成的围护结构的内力分配模式,并结合现场监测数据验证该理论的受力合理性。结果表明,由短地下连续墙与长工法桩组合而成的围护结构的内力分配基本符合刚度分配理论,由短地下连续墙承担大部分弯矩内力,由长工法桩控制整体基坑的稳定性。栈桥体系采用第一道混凝土支撑兼作栈桥梁,在桩基布置空间受限的情况下,基坑格构柱可埋于隧道中墙内,栈桥体系受力可满足基坑内力变形要求和施工期间社会车辆的通行需求,可为该地区类似的深基坑工程提供有益参考。

    Abstract:

    With the advancement of urban underground space development, the design of the foundation pit for newly-built tunnels should fully reserve the conditions for the long-term shield tunneling at the lower level. Focusing on the Shanghai Waiqingsong Highway Tunnel Project, and for the parallel development of new tunnels and long-term rail transit, the research is carried out on the design of foundation pits under the circumstances of temporary traffic restrictions during the construction period. A calculation model is established using the finite element software MIDAS GTS/NX to obtain the internal force distribution mode of the retaining structure composed of short underground diaphragm walls and long construction piles. And combined with the field monitoring data, the force rationality of this theory is verified. The result shows that the internal force distribution of the retaining structure composed of short underground diaphragm walls and long construction piles basically conforms to the stiffness distribution theory. The most of the bending moment internal forces are borne by the short underground diaphragm wall, and the overall stability of the foundation pit is controlled by the long construction pit method. A trestle system is used of the first concrete strut as a trestle beam. In the case where the space for pile foundation layout is limited, the lattice columns of the pit can be embedded within the central wall of the tunnel, the force-bearing capacity of the trestle system can meet the internal force deformation requirements of the foundation pit and the traffic needs of social vehicles during construction, which can provide a useful reference for similar deep foundation pit projects in this area.

    参考文献
    相似文献
    引证文献
引用本文

林楠.预留并行盾构穿越条件的深基坑设计与分析[J].城市道桥与防洪,2026,(3):316-321.