Abstract:In the design of the overall scheme for Jiaxing Avenue in Jiashan County, in response to the demand for rapidization within a 3.6 km range of the section shared with the planned urban railway, four overall schemes of elevated co-construction, tunnel separation, elevated separation and continuous underpass are proposed and compared. The rapidization scheme is optimized and determined through a systematic comparative analysis of multiple dimensions, such as railway construction requirements, mutual influence between rail-road composite channels, environmental landscape, alignment indicators and land use, which can meet the construction requirements under the constraints of combined rail and road lines. Meanwhile, the important nodes are compared and selected in combination with the main line function, ramp layout, railway, land use conditions and other restrictive factors, which can provide references for the design of rapidization reconstruction of similar roads of combined rail and road lines.