机场沥青道面不停航快速维修技术体系及应用
作者:
作者单位:

作者简介:

陈裕锋(1994—), 男, 本科, 工程师, 从事道路工程的施工与管理工作。

通讯作者:

中图分类号:

U414;U415.6

基金项目:


Technical System and Application of Rapid Maintenance for Airport Asphalt Pavement without Stopping Flights
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    机场道面维修需在保障飞行安全的基础上,最大限度降低对航班高效运行的干扰。传统水泥道面维修周期长(≥21 d),单次维修日均导致3~5架次航班停飞,难以适配机场高效运营需求。提出一套整合方案设计、材料选型、工艺优化、质量管控与安全保障的机场沥青道面不停航快速维修技术体系:通过夜间4 h施工窗口(01:00—05:00)设计“分阶段扩展围封”方案(初期1.5倍维修区、中期1.2倍、后期仅核心区),配套红外报警及双应急通道,15 min内可释放70%区域供航班滑行。材料选用符合高强度承载需求的沥青混合料,搭配温控运输(到场温度≥175℃)、限速摊铺(2.0~3.0 m/min)等优化工艺,单平方米工效达12 m2/人·时,较水泥道面提升4倍,维修后3 h即可开放交通;同步建立“时段-区域”双维质量检测体系及设备-应急-人员三重保障机制,确保施工全程零事故。该技术体系为机场道面快速维修提供了安全高效的整体解决方案。

    Abstract:

    Airport pavement maintenance should minimize the interference with the efficient operation of flights to the greatest extent on the basis of ensuring flight safety. Traditional cement pavement maintenance has a long cycle (≥ 21 d). Each maintenance operation leads to the grounding of 3 to 5 flights on average each day, which is difficult to meet the efficient operation requirements of the airport. A comprehensive technical system for rapid maintenance of airport asphalt pavement without stopping flights is proposed, which integrates the scheme design, material selection, process optimization, quality control and safety guarantee. Based on the 4-hour construction window at night (01:00~05:00), a “phased expansion enclosure” scheme is designed (initial 1.5 times maintenance area, mid-term 1.2 times and later only core area), which is equipped with infrared alarms and dual emergency channels to release 70% of the area for flight taxiing within 15 min. The materials selected are asphalt mixtures that meet the requirements of high-strength load-bearing, and are combined with optimized processes such as temperature-controlled transportation (arrival temperature ≥175 ℃) and speed-limited paving (2.0~3.0 m/min). The work efficiency per square meter reaches 12 m2/person·hour, which is 4 times higher than the cement pavement and can be opened to traffic 3 h after maintenance. Simultaneously, a dual-dimensional quality inspection system of “time period - area” and a triple guarantee mechanism of equipment - emergency response - personnel are established to ensure zero accidents throughout the construction process. This technological system provides a safe and efficient solution for rapid maintenance of airport pavements.

    参考文献
    相似文献
    引证文献
引用本文

陈裕锋.机场沥青道面不停航快速维修技术体系及应用[J].城市道桥与防洪,2026,(4):302-305.