Abstract:In recent years, the double-way 6-lane cross-section of the section from Guangling Interchange to Jingjiang Interchange in Beijing-Shanghai Expressway has been unable to meet the traffic demands. To enhance its operational capacity and meet the current traffic needs, it is planned to reconstruct it to a double-way 10-lane expressway by the two-side widening method. As the road section cannot be closed during the construction period, to ensure traffic efficiency, also to guarantee the construction and traffic safety, and to adhere to the principles of the traffic organization scheme, the construction countermeasures of simultaneous implementation, lane-by-lane traffic, phased breakthroughs and reasonable diversion are proposed for this project. The traffic organization is designed from two aspects of traffic organization and sub-project implementation during the construction period. According to the design scheme, the implementation results of each sub-project such as the roadbed and pavement, bridges and culverts, and interchanges show that during the reconstruction and expansion period, the operation of double-way 4-lane traffic at least in the road section should be guaranteed, which has the minimal impact on the social travel and the surrounding diversion road network. The construction period of the local road closure is approximately 21 months, and the total construction period is about 39 months. Throughout the construction period, one emergency rescue lane can be guaranteed at least.