复杂海域大跨悬索桥钢箱梁吊装与合龙关键技术
作者:
作者单位:

四川公路桥梁建设集团有限公司,四川 成都 610041

作者简介:

陆鹏(1990—), 男, 本科, 工程师, 从事道路与桥梁施工工作。

通讯作者:

中图分类号:

U445.4

基金项目:


Key Technologies for Steel Box Girder Hoisting and Closure of Long-Span Suspension Bridges in Complex Marine Environments
Author:
Affiliation:

Sichuan Road and Bridge Group Co., Ltd., Chengdu 610041, China

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    土耳其1915恰纳卡莱大桥主桥为770 m+2 023 m+770 m双塔三跨连续钢箱梁悬索桥,全桥加劲梁共有87个安装梁段,标准梁段长48 m,最大吊装重量可达838.8 t。同时大桥受地理环境、强风以及通航的影响,钢箱梁安装存在很大的技术难度和安全风险。根据现场情况,钢箱梁主跨由跨中向主塔方向对称吊装,边跨由锚碇向主塔方向对称吊装,后于主塔位置进行合龙。在施工过程中,边跨的非标准梁段采用驳船运输+5 000 t浮吊的方式安装;标准梁段与中跨跨中梁段采用驳船运输+1~2台450 t缆载吊机的方式安装;2#梁段采用驳船就位、反向荡移提升系统+2台450 t缆载吊机同步提升的方式安装;主塔合龙区梁段先使用浮吊吊装在焊接平台调整、焊接,后采用边跨反拉系统+4台450 t缆载吊机同步提升的方式安装。

    Abstract:

    The main bridge of 1915 ?anakkale Bridge in Turkey is a double-pylon three-span continuous steel box girder suspension bridge with the spans of 770m + 2 023 m + 770 m. The entire bridge consists of 87 girder segments for the stiffening truss, with a standard segment length of 48 m and a maximum hoisting weight of up to 838.8 t. At the same time, the bridge is affected by geographical conditions, strong winds and navigation, which makes the erection of steel box girders highly technically challenging and poses significant safety risks. According to the site conditions, the main span of the steel box girder is hoisted symmetrically from the midspan towards the main pylon, while the side spans are hoisted symmetrically from the anchorages towards the main pylon. Then, the closure is carried out at the position of the main pylon. During the construction process, the non-standard girder segments of the side spans are erected by using barge transportation combined with a 5000t floating crane. The standard girder segments and the midspan girder segments are erected by using barge transportation combined with 1-2 sets of 450t cable-mounted crane. The No.2 girder segment is erected by using barge positioning, a reverse swing lifting system, and synchronized lifting by 2 sets of 450t cable-mounted cranes. The girder segments in the main pylon closure area are first hoisted by a floating crane onto a welding platform for adjustment and welding, and then erected by using a side span counter-pulling system combined with 4 sets of 450t cable-mounted cranes for synchronized lifting.

    参考文献
    相似文献
    引证文献
引用本文

陆鹏.复杂海域大跨悬索桥钢箱梁吊装与合龙关键技术[J].城市道桥与防洪,2026,(11):325-330.

复制
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2005-08-22
  • 最后修改日期:2026-05-30
  • 录用日期:2026-06-01
  • 在线发布日期: 2026-11-18
  • 出版日期:
关闭