Abstract:The main bridge of 1915 ?anakkale Bridge in Turkey is a double-pylon three-span continuous steel box girder suspension bridge with the spans of 770m + 2 023 m + 770 m. The entire bridge consists of 87 girder segments for the stiffening truss, with a standard segment length of 48 m and a maximum hoisting weight of up to 838.8 t. At the same time, the bridge is affected by geographical conditions, strong winds and navigation, which makes the erection of steel box girders highly technically challenging and poses significant safety risks. According to the site conditions, the main span of the steel box girder is hoisted symmetrically from the midspan towards the main pylon, while the side spans are hoisted symmetrically from the anchorages towards the main pylon. Then, the closure is carried out at the position of the main pylon. During the construction process, the non-standard girder segments of the side spans are erected by using barge transportation combined with a 5000t floating crane. The standard girder segments and the midspan girder segments are erected by using barge transportation combined with 1-2 sets of 450t cable-mounted crane. The No.2 girder segment is erected by using barge positioning, a reverse swing lifting system, and synchronized lifting by 2 sets of 450t cable-mounted cranes. The girder segments in the main pylon closure area are first hoisted by a floating crane onto a welding platform for adjustment and welding, and then erected by using a side span counter-pulling system combined with 4 sets of 450t cable-mounted cranes for synchronized lifting.