Abstract:Taking the project of a long-distance water conveyance pipeline passing under a highway in Yangzhou City as an example, the entire process of pipe jacking construction is restored based on numerical models. Four parameters of soil cover thickness, pipe diameter, tunneling pressure and grouting pressure are selected for single-factor sensitivity analysis to determine the optimal construction process parameters. The results indicate that soil cover thickness and pipe diameter have the most significant impact on the pavement settlement, while the influence of tunneling pressure and grouting pressure is weaker. The optimal parameter combination is comprehensively determined as soil cover thickness 14.0 m, pipeline diameter 3.5 m, tunneling pressure 200 kPa, and grouting pressure 100 kPa. Under these conditions, the maximum pavement settlement is 8.24 mm, meeting the 10 mm specification limit. Field measurements show that a maximum settlement is 8.45 mm, with a relative error of only 2.55% compared to numerical simulation results, verifying the accuracy and feasibility of the numerical model and optimization scheme.