Abstract:Aiming at the problems of disjointed technology and economy and extensive cost management in prefabricated box girder projects, the cost control and optimization are studied based on the precast small box girder project of Yangshan Port collection and distribution project. Combined with the full-cycle production data of 204 precast box girders, a lean cost management system is constructed from five dimensions of site planning, capacity matching, resource allocation, quality control and safety risk quantification by comprehensively applying break-even analysis, PAF quality cost model, LEC safety assessment method and OEE equipment comprehensive efficiency model. The practice show that the management mode realizes the dynamic matching between production capacity and construction progress with the overall equipment effectiveness reaching 86.5%, and effectively reduces the hidden costs, rework costs and safety losses. The relevant optimization strategies can provide practical references for reducing costs, increasing efficiency, improving quality and ensuring safety in similar prefabricated component projects of large-scale transportation hub.