Abstract:In urban underground engineering, the spatial conflict between deep-buried pipelines and diaphragm walls of foundation pits has become a key bottleneck restricting the construction safety and efficiency. Based on an underpass tunnel project of an expressway in Gongshu District, Hangzhou, an integrated technical system of “accurate positioning - classified obstacle clearance - layered reinforcement - dynamic monitoring” is systematically developed for the complex working conditions where multi-material deep-buried pipelines such as ductile iron sewage pipes, steel pipes and PE water supply pipes intersect with diaphragm walls. By optimizing the cutting parameters of the full-rotary drilling rig, innovating the verticality control technology of high-pressure jet grouting piles, and establishing a three-level early warning monitoring mechanism, the safe and efficient obstacle clearance of deep-buried pipelines under complex geological conditions is realized. Engineering practice shows that this technology can control the settlement of surrounding pipelines within 15mm, and the qualified rate of diaphragm wall trenching reaches 100%, which solves technical problems such as limited space construction under high-voltage overhead lines and collaborative obstacle clearance of multiple types of pipelines, providing a replicable technical scheme and engineering example for similar projects in urban core areas.