桥梁整体顶升钢支撑与同步控制关键技术研究
作者:
作者单位:

上海隧道工程有限公司,上海市 200032

作者简介:

陆涛(1989—), 男, 本科, 工程师, 从事桥梁施工工作。

通讯作者:

中图分类号:

U443;TU997

基金项目:


Research on Key Technologies of Steel Supports and Synchronous Control for Integral Bridge Jacking
Author:
Affiliation:

Shanghai Tunnel Engineering Co., Ltd., Shanghai 200032, China

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对城市快速路改造大纵坡多联连续梁整体顶升存在同步控制精度偏低、超高钢支撑稳定性不足、梁体纵向伸缩诱发水平偏移等难题,依托上海S32立交盐朝公路跨线桥(最大顶升高度6.489 m)工程,研发适配超大高差纵坡工况的一体化顶升成套技术。提出“交替分级顶升+格构钢管支撑+模糊PID双闭环液压同步+三维动态纠偏”技术体系;结合几何变形理论、MIDAS屈曲仿真、PLC控制算法优化与现场全参量监测开展系统研究。研究结果表明,顶升同步精度≤0.5 mm,4×4?609×16格构支撑一阶稳定系数为17,协同纠偏可控制梁体水平位移≤5 mm。相较拆建方案,成本降低35%、工期缩短40%、全生命周期碳排放减少42%,可为同类工程提供理论依据与标准化施工范式。

    Abstract:

    Aiming at the problems such as low synchronous control accuracy, insufficient stability of ultra-high steel supports, and horizontal displacement induced by longitudinal expansion and contraction of the beam body in the overall jacking of large longitudinal slope multi-span continuous beams in urban expressway renovation, relying on the Shanghai S32 Interchange Yanchao Highway Overpass Project (with a maximum jacking height of 6.489m), a complete set of integrated jacking technology suitable for the working conditions of super-large height difference longitudinal slope has been developed. A technical system of “alternating staged jacking + lattice steel pipe support + fuzzy PID double closed-loop hydraulic synchronization + three-dimensional dynamic deviation correction” is proposed. A systematic study is carried out by integrating geometric deformation theory, MIDAS buckling simulation, PLC control algorithm optimization and on-site full-parameter monitoring. The results show that the synchronous jacking accuracy is ≤ 0.5mm. The first-order stability coefficient of the 4×4?609×16 lattice support is 17. The coordinated deviation correction can control the horizontal displacement of the beam body ≤ 5mm. Compared with the demolition and construction schemes, the cost is reduced by 35%, the construction period is shortened by 40%, and the carbon emissions throughout the life cycle are reduced by 42%, which can provide a theoretical basis and standardized construction model for similar projects.

    参考文献
    相似文献
    引证文献
引用本文

陆涛.桥梁整体顶升钢支撑与同步控制关键技术研究[J].城市道桥与防洪,2026,(11):401-406.